N.C.G.S. § 143-134.3 — revision history

Text is never overwritten. Each amendment lands as a new version row with its own effective range.

  1. Version 12026-08-08 to present

    Scraped from ncleg.gov; The General Statutes include changes through S.L. 2026-7.

    No contractual language forbidding or limiting compensable damages for delays caused solely by the owner or its agent may be enforced in any construction contract let by any board or governing body of the State, or of any institution of State government, or of any county, city, town, or other political subdivision thereof. For purposes of this section, the phrase "owner or its agent" does not include prime contractors or their subcontractors. (1997-489, s. 1.)